Transformer LV Short-circuit Impedance
Tester applies to LV load impedance test during delivery, overhaul, trial test and handover test of
power transformers (single phase or three-phase).
It tests the short-circuit impedance (%) of
power voltage on site and compares it with the value indicated on the nameplate
or the factory default to find out any defects including but not limited to
winding displacement or deformation due to currents from major failure during
transformation, installation or operation following the delivery test. (The
short circuit change shall be considered as significant if it exceeds ± 3% as
specified in China International Conference on Electricity Distribution 2000
(“CICED 2000”)).
Transformer LV Short-circuit Impedance
Tester is not provided with an external voltage regulator and adopts the
primary connection mode. It begins the three-phase testing and calculates
impedance error percentage automatically when the parameter is entered and
provides intuitive results. This is a rapid tester which detects winding
deformation of transformers on site.
I. Technical Parameters(LYBDS6000E Transformer Short-circuit Impedance Tes)
|
Scope of voltage measurement: 5~400V
|
Accuracy of measurement: 0.2d
|
|
Scope of current measurement: 0.1~20A
|
Operating power: AC220V±10%
|
|
Power frequency: 50Hz
|
Operating temperature: -10℃~50℃
|
|
Ambient humidity: ≤85%RH
|
Net weight: 8kg
|
II. Characteristics(LYBDS6000E Transformer Short-circuit Impedance Tes)
1. The
tester is supplied with AC220V low voltage power to provide current for AB, BC
and CA high voltage windings of the transformer automatically; collects data
simultaneously and; calculates impedance error percentage automatically with
intuitive testing results;
2. The
tester completes the three-phase testing automatically in the primary connection
mode other then inversed connection with the testing wire;
3. The
tester allows either single phase testing or three-phase testing both manually
and automatically;
4. The
tester achieves output current limit applicable to test item with any impedance;
5. The
test item can be measured without an external voltage regulator;
6. The
tester functions in measuring zero sequence impedance;
7. The
tester functions in measuring inductance;
8. The
tester has a large LCD display with a menu in Chinese. Operation are facilitated
based on the notes on the display;
9. The
tester enables printing and storage and is featured with high testing accuracy,
high automation, small in size and light weight.
III. Wiring Diagram(LYBDS6000E Transformer Short-circuit Impedance Tes)
● Fig.
A depicts the wiring of a single phase transformer
● Fig.
B depicts the wiring of a three-phase dual-winding transformer

● Wiring
of the three-phase dual-winding transformer is consistent with the selected
position to be measured. If a High-Low position is selected for measurement,
the testing wire should be connected to the HV side while the LV side is under short circuit; the remaining
wires are under open circuit. If a High-Medium position is selected, the
testing wire should be connected to the HV side while the medium voltage side
is under short circuit; the remaining wires are under open circuit. If a Medium-Low
position is selected, the testing wire should be connected to the medium
voltage side while the LV side is under short circuit; the remaining wires are under open circuit.
● The
section of short circuit wire should be no less than 10 mm2 (bare copper wire
is preferred). Such wire should be in good contact; otherwise it will affect
the accuracy of testing data.
IV. Operating Instructions:
1. The
interface shows when the tester is powered on: (Interface 1)
2. Push down ENT to enter into the
parameter setting interface: (Interface 2)
3. Enter
the data on the transformer nameplate according to notes on the display. Push
down ↑↓ to select a line. Push down ← to delete a digit towards the left. Push
down the numeric keys to enter a digit. If negative testing temperature is
needed, first push down ← to delete the digit, then push down ↓ to adjust a
positive/negative sign; enter the temperature data and push down ENT to go to
the interface below: (Interface 3)
Note:
● The
input of rated voltage should be consistent with the tapping position.
● If
the single-phase process is used for a three-phase transformer, the data to be
entered should be 1/3 of the rated capacity.
4. Select
a single phase transformer or a three-phase transformer to be measured.
● Measurement
of a single phase transformer:
① Connect the testing wire between the tester
and the transformer as shown in Fig. A of the wiring diagram. Enter the
parameter. Select Single Phase in Interface 3. Push down ENT and it will show
as follows: (Interface 4)
② Push down ENT to start measurement. The
testing results will be shown on the display. The interface will show as
follows: (Interface 5)
③ Push down ENT to stop
when the desired value of testing data is achieved. The testing data will be
locked.
④ After locking the data,
push down Print to directly print the test report.
⑤ Push down SAVE. An “ALL
DONE” notice will show at the lower right corner. If it is stored in the
U-disk, please return to the “Welcome” interface when the tester is powered on.
Press SAVE and the display will show all records saved. Select a record, insert
the U-disk and press SAVE to save it in the U-disk. An “ALL DONE” notice will
show at the lower right corner of the display.
● Measurement
of a three-phase transformer – manual measurement:
① Connect the testing
wire between the tester and the transformer as shown in Fig. B of the wiring
diagram. Enter the parameter. Select Three-phase in Interface 3. Push down ENT
and it will show as follows: (Interface 6)
② Push down ← → to select
the Manual or Auto mode. If Manual is selected, push down ENT to show three
connection modes of the transformer: Y/△, Y/Y, △/Y, as
shown below: (Interface 7)
Notes:
a.The
connection mode in Interface 7 should be selected based on the connection group
of the transformer terminal.
b.Note:
For the Medium-Low position of the three-phase three-winding transformer, Y
denotes medium voltage and the low voltage side is under short circuit. Y/△ or Y/Y
may be selected without allowing the connection mode of low voltage.
c.Push
down ← → to select the connection mode of the transformer. If △/Y is
selected, two different connection modes of △ mode will show: AZ-BX-CY
or AY-BZ-CX to be determined by user according to conditions of the test item.
③ After selecting, push down ENT to go to the
interface below: (Interface 8)
④ Push down ← → to select the current applied
AB, BC or CA phase. If AB phase is selected, push down ENT to measure the
voltage and current of AB phase, as shown below (Interface 9):
⑤ Push down Ent to lock
the data. Push down Ent again to select the status of BC phase. Push down ← →
to select BC phase, as shown below (Interface 10):
⑥ Push
down ENT to measure the voltage and current of BC phase, as shown below:
(Interface 11)
⑦ The testing procedure
of CA phase is the same as above. When the data of CA phase is locked, the
tester will give an integrated calculation for the testing data of manual
single phase for three times automatically. The display will show the impedance
testing results and provide a printed report after two seconds.
An interface will show as follows: (Interface
12)
⑧ Push down Print to
directly print the test data report (the same with subsequent three-phase auto
report).
⑨ Push down SAVE to save
it in the tester. An “ALL DONE” notice will show at the lower right corner. If
it is stored in the U-disk, please return to the “Welcome” interface when the
tester is powered on. Press SAVE and the display will show all records saved.
Select a record, plug in the U-disk and press SAVE to save it in the U-disk. An
“ALL DONE” notice will show at the lower right corner of the display.
⑩ Push down ESC to return
to the parameter setting interface from the testing interface. The manual
single phase measurement of a three-phase transformer ends.
● Measurement
of a three-phase transformer – three-phase auto measurement:
① Push down Ent after
entering the data. Select the three-phase transformer, as shown below:
(Interface 13)
② Push down Ent. Press ← → to select Auto
mode, as shown below: (Interface 14)
③ Push down ENT. Press ← → to select the connection mode, as shown
below: (Interface 15):
Notes:
a.The
connection mode in Interface 15 should be selected based on the connection group
of the transformer terminal.
b.Note:
For the Medium-Low position of the three-phase three-winding transformer, Y
denotes medium voltage and the low voltage side is under short circuit. Y/△ or Y/Y
may be selected without allowing the connection mode of low voltage.
c.Push
down ← → to select the connection mode of the transformer. If △/Y is
selected, two different connection modes of △ mode will show: AZ-BX-CY
or AY-BZ-CX to be determined by user according to conditions of the test item.
④ Push down ENT to go to
the interface below: (Interface 16)
⑤ Push down Ent to
measure. The tester applies current to the windings of AB, BC and CA phases,
collects data automatically and locks the measurements of three phases in turn.
After measuring, the tester calculates impedance error automatically.
The display will show the measurements:
(Interface 17)
⑥ Push down Print to directly print the test
report below:
⑦ Push down SAVE to save
it in the tester. An “ALL DONE” notice will show at the lower right corner. If
it is stored in the U-disk, please return to the “Welcome” interface when the
tester is powered on. Press SAVE and the display will show all records saved.
Select a record, plug in the U-disk and press SAVE to save it in the U-disk. An
“ALL DONE” notice will show at the lower right corner of the display.
● Measurement
of a three-phase transformer – single phase measurement:
If the single-phase process is used for a
three-phase transformer, the data to be entered should be 1/3 of the rated
capacity.
The connection and operating mode should be
the same with that of a single-phase transformer.
● Measurement
of zero sequence impedance: When the zero sequence impedance is measured, the
connection mode should be in such a manner that the HV three phases should be
in parallel while the low voltage is under short circuit. Operations are
provided as follows:
① Select Zero Sequence
Impedance in Interface 3 as follows: (Interface 18)
② Push down Ent to
measure. The measurement results are shown below: (Interface 19)
③ Push down Ent to lock.
Push down Print to directly print the test report below:
④ Data storage and
storage in the U-disk are the same with that of impedance testing.
● Test result judgment reference
The impedance error is less than 2% : the
transformer can run normally
Impedance error in 2%-5% : transformer
periodic detection
Impedance error over 5% : transformer
should be shut down
V. Packing List
|
Tester
|
1 Set
|
|
Private wire
|
1 Set
|
|
Power wire
|
1 Piece
|
|
Ground wire
|
1 Piece
|
|
Line box
|
1 Piece
|
|
Fuse
|
4 Pieces
|
|
Product manual
|
1 Piece
|
|
Test report
|
1 Piece
|
|
Product certificate
|
1 Piece
|
|
Typing paper
|
1 Roll
|
VI. Order and Service
1.A
one-year free warranty is given to products subject to quality problems since
the date of manufacture; materials costs will be charged for any damage due to
other causes. Costs of repair and maintenance will be only charged if it is out
of the free warranty.
2.We
provide lifetime maintenance and technical services for the products.
3.Please
contact us immediately upon discovery of any abnormality in the tester . We
will provide the most convenient solution for you. DO NOT disassemble the tester!